Tag Wolf Construction install the septic tank and drain fields.  After the State and County inspections, Tag backfilled the tank.  The weekend of August 8th, Ray and Lynette delivered Ray's new tractor for us to use on the project.  It has forks, bucket, and Ray built a man lift for the forks that came in real handy.  We finished the drain mat around the building, installed the drain pipe and drain rock so that we could backfill the foundation while Ray was there to run his tractor.

 

 

 